Calculation of Benefits About Water for Environmental Use of Feasibility Study of Baekgok Dam Embankment Raise Project

ClientKorea Development Institute

Year2010 - 2010

LocationJincheon, Korea

Scale Project Summary : Bacgok Dam Embankment Raise, Project Scope - Embankment Raise : 2.0m(27.2 ⇒ 29.2m)
- Floodgate Installation : 9.5m × 7.7m × 4
- Road Relocation : 1set 2.4㎞(w 6.0m Asphalt Concrete Pavement)