List
ENGINEERING Water Sewerage

Preliminary and Detailed Design for Cheonho-1 Sogu Subarea Sewer Pipeline Rehabilitation Project

ClientSeoul City

Year2022 - 2024

LocationCheonho, Korea

Scale Site Area : 204.82ha
Route Survey : 39.6㎞
Soil Investigation : 3 locations
Flow and Water Quality Assessment : 5 locations
Total Length of Targeted Pipelines : 74.8㎞

The purpose of this is to derive improvement measures for enhancing the functionality and quality of sewage pipelines and to establish detailed construction and maintenance plans to realize these improvements.

  1. #Seoul
  2. #Domestic
  3. #Sewerage
List