Preliminary design for renewal and new installation of Yongin Respia in Yongin
ClientGS E&C
Year2015 - 2015
LocationYongin, Korea
Scale
Sewage Treatment Plant Capacity : 56,000㎥/day (renewal and new installation)
Reclaimed Wastewater Faciliy : 20,000㎥/day (Mapyeong Marshy Land)
Reclaimed Wastewater Pipe Line : D600㎜, L=11.2㎞
The purpose of this project is to perform the basic design required for the Turn-key bidding of the Yongin L'Resphia improvement and expansion project. This design is based on the conditions provided by the client and aims to achieve the optimal design, considering the reliability, stability, constructability, and cost-effectiveness of the facilities. It also includes facility planning that takes into account operation and maintenance. This involves adhering to the specified water quality standards outlined in the bidding guidelines while maintaining coordination with local conditions and interrelated aspects of various fields. By ensuring compliance with the provided instructions, including task orders, bidding instructions, basic project reports for sewage system improvement, and other relevant materials, the goal is to carry out the construction of facilities that enable efficient operation. The ultimate objective is to secure a competitive advantage in terms of technical expertise and construction costs compared to other competitors during the bidding process, thus winning the contract for this project.